Massachusetts College of Liberal Arts Berkshire Towers Elevator Replacement Project Number: MCLA 0907-20 Completion date: Summer, 2021 Status: Construction Architect: Livermore Edwards & Associates Construction Manager: D A Sullivan & Sons Owner's Project Manager: C3 - Commercial Construction Consulting Project Manager: Paul Forgione
The MSCBA commissioned an Elevator study for Hoosac Hall and Berkshire Towers from VDA Consulting. The study indicated the Berkshire Towers elevators should be considered for a long term modernization within the next two to four years. Due to recurring maintenance issues with both A and B Towers elevators in early March 2020 we are proceeding with renewal design immediately. This renewal/replacement is being planned for May 2021. MSCBA Has contracted with VDA and Livermore Edwards for the elevator design. The General Contractor D.A. Sullivan was chosen under Chapter 149.